3.1 Supplier Selection

Selection of potential suppliers for a large project is an important step, and needs to be given sufficient time and attention. Nuclear power plant vendors may partner with different sub-suppliers for different projects, and need sufficient notice periods to make necessary arrangements for such partnerships. This includes meeting any owner pre-qualification requirements.

Suppliers working in an international context face a number of unique challenges or differences from their home countries. These can include:

  • Cultural and language barriers (e.g. work habits, holidays, length of work day)
  • Differences in organizational safety culture and experience in a nuclear environment
  • Inexperience with capabilities of local sub-suppliers
  • Currency fluctuations
  • Time zone differences (making communication more difficult)
  • Export control rules specific to the country (from home country or country of sub-suppliers)
  • Differences in duties, taxes, legal, insurance or political regimes
  • National or regional technical differences (management system used, codes, standards, or inspection requirements, e.g. electrical voltage and frequency, SI versus Imperial units of measure)
  • Logistics issues (shipping methods (especially for large components (e.g. rail, highway or port changes that may be needed, special transport or heavy lifting equipment), customs clearance methods and delays)
  • Need to assess whether to ship, store, purchase locally or rent equipment for use at remote job sites
  • Safety and security of international workers (and fewer backups if an international worker is sick or otherwise off work)

This section discusses some of the issues involved with supplier selection.